Turkey Island Cable Installation
Project Description: Crofton Industries installed 1400 feet of cable in Chesterfield, VA using directional and horizontal drilling. The installation occurred on Federal property requiring additional considerations for regulatory constraints. Minimal ground disturbances were required to avoid possible artifacts. Crews drilled 60' below existing mud line using a directional drilling unit with 220 lbs of push/pull capacity.
Project Location
Chesterfield, VA
Construction Elements
HDD Operations
Marine Transport Operations to Mobilize to an Island
Open Trenching